Project management







Deadline :- 5th Jan 20      6:00 pm 

Message:-

I have attached the draft group assignment of project management, as a group member, my role is limited to the following:

Can you help to writeup 02 context as mentioned below, which should include some useful diagram of communication management and risk plan?

1.    Detail of risk assessment and appropriate application of risk analysis to managing project outcomes  - 500 words excluding diagrams or figures
2.    Appropriate level of Communication management, with key stakeholders, identified, with a basic communication plan.  - 500 words, excluding diagrams or figures. 

 PROJECT MANAGEMENT – ASSIGNMENT 2 (Group SUBMISSION)
[Document subtitle]

DECEMBER 15, 2019
S3, 2019
Student number: 30327088
 
 




Assessment Task 2: Project Charter

 (Please don’t remove this page)

1)            Assessment Details
You are to develop a Project Charter (long version), identifying a need for change within your business, and develop the components required to “sell” the project, including any resources to deliver the proposed change, to senior management in your business.

2)            Criteria used to grade this task
The Project Charter should clearly identify the strategic change proposed, expected outcomes, key milestones and deliverables.  Detailed marking criteria can be found in the Marking Guides section of this course description.

Assignments will be examined by software to detect any suspected instances of plagiarism and collusion. Assignments will be compared to other assignments submitted previously

Additional guidance:

This is an academic assignment, so it is essential that your statements and views be justified by relevant academic theory. For example, don’t just use terms like ‘stakeholder’ – explain why you selected those terms, and the academic theory to justify their use and definition.
A major failing of students is to simply ‘describe’ the processes that have happened. At this level you are expected to be able to apply recognised theory to situations, and form opinions. You will often find conflicting opinions from so-called ‘experts’. You should be developing analytical and communication skills.




Mark Sheet
(Please don’t remove this page)
Assessment Task 1 Feedback: Individual Report: Project Charter
Assessment Criteria
Comments
Mark
Report content and structure, including flow, executive summary.
(2 Marks)


Background, business needs, and reasons for doing the project clearly defined.
(5 Marks)


Project Scope well described including objectives, major deliverables, milestones, success criteria and constraints.
(8 Marks)


Detail of risk assessment and appropriate application of risk analysis to project selection
(5 Marks)


Major stakeholders and project roles identified, with initial communication requirements outlined.
(5 Marks)


Quality and accuracy of financial analysis
(3 Marks)


In-text references and reference list
(2 Marks)


Total Marks
(30 Marks)




Comments






Lecturer


Date







Contents


1. Appendix 1 – OTC PPN expansion risk and mitigation plan                                                                              0



1.      List of Tables







2.      List of Figures




Executive Summary

Onsite Testing & Calibration (OTC), Australia’s leading calibration, testing and inspection company has the opportunity to be awarded a utilities maintenance contract in Western Australia worth $1.5 million per year in revenue with prospective client, Perth Power Networks (PPN). Should this contract be awarded, OTC will be required to increase internal resources for in order to service the contract. This project charter has been requested from the internal department known as the technical team in order to explain and document the preliminary work that has been completed along with the submission of the project tender and provide the basis for an assessment for a final investment decision from the OTC executives. While the contract is still in the tender stage, OTC is of the opinion that there are no other companies in Australia who have the capacity to service it to the level it requires. This project charter is expected to be invaluable and serve as a project steering document – particularly from a stakeholder and communications management perspective when OTC is announced as the successful party.
Preliminary investigative works have composed of:
●        Additional asset requirements
●        Staffing requirements
●        Risk assessments and mitigation strategies
●        Stakeholder management & communication requirements
●        Analysis of the process involved in acquiring, onboarding and planning to complete these works while at the same time maintaining the same level of service to existing clients and scopes of works.
This expansion project aligns with OTC internal mission statement of “Crush X” where X is the redacted name of OTC’s main competitor. As well as aligning with all six OTC values:
  1. Be awesome – OTC will be awesome and “world champions” in executing this contract
  2. Always Yes – OTC will say yes to this contract if it’s offered. As well as saying yes to the client’s preferred start date
  3. Positivity – OTC will be positive at all times during the project, as a smile is free, and the positives for the business should this contract be awarded are exceptional
  4. Dot Your I’s – OTC will ensure this project is delivered to the expected high levels of quality and accuracy
  5. Gratitude – The business is aware this contract could have been awarded to another provider. Therefore, OTC will ensure that the project is completed in order to give back to the client for providing a growth opportunity benefiting the entire business
  6. Own It – Internal stakeholders will complete their assigned tasks and assist their colleagues when required to complete this work and allow the other values to be adhered to.
OTC’s external mission statement of “Making Compliance Effortless” will be paramount for every decision made in the planning and execution of this project. As ultimately, this is what it is about. Once this is addressed, the values and the internal mission statement will also be met.



1.    Project background, business need, and reasons for the need for the project


1.1 Project Background

Onsite Testing & Calibration (OTC) has the opportunity to become the major provider, calibration and inspection services in the Australian marketplace with the award of a significant contract in Western Australia to service the Perth Power Network (PPN).
To service this contract, OTC needs to undertake its biggest expansion project in company history; improving on previous expansions by applying lessons learned to safety, effectively and efficiently build and deploy mobile calibration laboratories into Western Australia in order to service this contract. Aligning with business goals of continuous growth, customer service excellence, “being awesome” and capturing more market share that will in turn limit the availability of work for competitors and force them to re-evaluate their operational feasibility (Larson, Honig, Gray, Dantin, & Baccarini, 2017). This project will better support the existing WA team as the additional resources provide a secondary benefit of being able to better service the wider local market outside the scope of the PPN contract.

1.2 Business Need & Reasons for Need of Project

Increasing competition is forcing business to provide better customer service and focus (Larson; et al 2017). A key element of OTC’s unique selling point is our value of ‘always yes’, this customer focus differentiates OTC from competitors and has been identified as a key driver for this expansion project for W.A. Without this expansion the WA branch of the business is under increasing pressure to justify additional resources being deployed in the market; and the business will be unable to service a potential contract it is tendering for. This creates the potential that due to incremental business growth and the award of the PPN contract, the customer experience could suffer. As also discussed by Larson; et al (2017) projects can also be used to gain market share and pressure competitors, which is another key aspect and driver of this project.

OTC’s potential award of the PPN contract will come at the expense of a large competitor and the final remaining barrier to obtaining the majority market share in Australia and New Zealand of any rival. It is not unreasonable to expect the competitor’s business model to no longer be viable as OTC complete the expansion project and begin work on the PPN contract.

The additional resources in W.A will all but guarantee almost complete market coverage, providing the business the ability to cover the market and to push the business’ relentless focus on safety and quality wider, in order to improve the overall market Australia wide. As a primarily service operating business the expansion will meet the classification of a project as it has specific characteristics as outlined by Larson; et al (2017), as can be found in table 1 below:

Table 1 – OTC PPN expansion project definition
Criteria that defines a project
OTC Deliverable
  1. Objective
Deliver new mobile calibration and testing laboratories to Western Australia
  1. Life Cycle
Build and Deliver of assets to Location
  1. Business involvement
Multiple Departments:
Executive
Finance
Operations
Technical
Management
Field staff
External Subcontractors
  1. Unique Deliverable
Scale of expansion not previously attempted by business
  1. Constraints & Requirements
Time Deadlines
Fixed budget limits
Quality, Safety and Environmental requirements
Source: adapted from Larson; et al (2017)














2.    Project Scope well described including objectives, major deliverables, milestones, success criteria and constraints


2.1 Project Scope

As this expansion is being conducted in line with ongoing operations and using mostly existing staff members, it is essential that the project scope is defined and specific goals are set, as this definition also prevents scope creep and therefore budget/time blowouts (Larson; Et al 2017). OTC’s PPN Expansion Project will expand capabilities and resources simultaneously in the W.A market. Previously, single labs have been added from organic growth, however due to the PPN contract the business will be required to put three additional calibration labs on the road simultaneously. All development of laboratories before deployment will be conducted simultaneously with regular operations at the Queensland (QLD) head office, with no interruptions to usual service levels or budget achievements by the business. Local subcontractors and previous suppliers will be utilised, again, just on a larger scale than previously. All capital expenditure (capex) funding will be financed, as the business has known costings for these items and is therefore able to implement this project with a relatively known budget. Incidental costs are to be approved in line with financial delegation levels as outlined in position descriptions.
Additionally, three new staff members will be simultaneously recruited, on boarded and trained. This process also be conducted with no disruption to ongoing operations, and indeed, training will be used to support ongoing operations.  All aspects of the project will be completed in line with OTC policies and procedures, therefore meeting all health, safety, environmental and quality (HSEQ) requirements for the business. The timeline for this project has been set at 16 weeks, of which only the training component can be extended. As discussed by Jaber, Marle, Vidal and Didiez (2018), project delivery and timelines require expert strategy and organisation. OTC believes it has the experience form past expansions to successfully increase the expansion scope to deliver this project despite the significant increase in project size.
The project will conclude when the new technicians have completed their four-week induction and training program in line with the integrated management system requirements (IMS), and all training documentation is completed to deem these employees competent to work unsupervised in the field.

2.2 Major Deliverables

It is accepted that the argument proposed by Jaber, Marle, Vidal and Didiez (2018) is accurate; deliverable management is a core key element of a project and a strategic decision made about the motivations and drivers of a project. Therefore, OTC executives demand the following deliverables must be completed in line with their target/due dates for the project to be completed successfully:
●        New vehicles built, fitted out and delivered into WA before the end of the 12th week of the project
●        Three new staff hired, on boarded and inducted by the end of week 12
●        New staff trained and deemed competent by the end of week 16, with final signoffs complete

2.3 Milestones & Schedule

In alignment with transparency for senior management’s ongoing assessment & monitoring on this project as well as for guidance and segregation of middle management’s respective roles in the project, OTC has developed a milestone schedule as scheduled by Larson; Et al (2017) in order to both define and provide deadlines that progressive milestones must be completed by in order for the project to remain on schedule. Additionally, as discussed by Hameri & Nihtila (1997), Project milestones are essential in coordination of projects with distributed team members. As OTC management works across multiple locations and time zones, having defined milestones with due dates allows for greater control and steering of the project by the COO when acting as PM. Table 2 below displays OTC PPN Expansion project milestones and their target/due dates
Table 2: OTC PPN Expansion project milestones & target/due dates
Project Milestone
Target/due date
Order all items required for builds
End week 1
Receive vehicles
End week 3
Preliminary fit out in house & schedule subcontractors to fit out vehicles
End week 4
Complete fit out of vehicles
End week 7
Select candidates for interviews & signwriting on vehicles
End week 8
Hire candidates
End week 9
Install all items into vehicles
End week 10
Deliver vehicles to Western Australia
End week 11
New employees start
Start week 12
Trainee signoff
End week 16

2.4 Success Criteria and Constraints

It has been decided that the key element to success and the biggest constraint this project will face is the ability of all stakeholders to effectively communicate, and communicate when required. There are a significant number of internal and external stakeholders who’s needs and expectations must be met. In line with OTC Quality system and ISO 9001 requirements, these needs and expectations will be understood and addressed appropriately through the project (International Organisation for Standardization, 2016). A communications plan will be developed in line with topics discussed by Larson; Et al (2017) & Stackpole (2010) in line with PMBOK frameworks and techniques. This communications plan will allow for ISO 9001 requirements to be met as we will know and understand the needs of all stakeholders, as well as have a plan in place for all parties to communicate effectively and succinctly. For OTC succinct and effective communication is critical to not just the success of this project, but the success of ongoing operations during the project.
The success of this project will focus around the deliverables and the project milestone/schedule dates, which is in line with discussions by Larson; et al (2017) and Stackpole (2010) as milestones that have due dates are an effective means of ongoing monitoring and success. For OTC, the due dates are critical and cannot be missed due to contractual obligations that the business is now under. Therefore, the due dates in the milestone schedule will be the main measurement of success. It is also naïve not to factor budget overruns in any discussion of project success. As OTC has relatively known costings and access to proforma invoices/quotes from its international suppliers that were gathered in preparation for the potential award combined with pricing from previous builds, relative costs/budgets are known Thus avoiding the risk of cost underestimation in order to improve perceived viability of a project as argued by Flyvbjerg, Holm & Bhul (2003). However, the variance to these costs will also need to be monitored and checked to ensure that the budget does not blow out and impact the short-term viability of the project and the business overall (Larson; et al 2017 & Snyder Stackpole 2010).










3.     Detail of risk assessment and appropriate application of risk analysis to project selection


Project risk is difficult to quantify as an overall term. However, all projects have inherent and individual risks that must be identified, assessed and mitigated (If possible) as discussed by Larson; et al (2017); unless once quantified the level of risk posed makes a project unviable, then the project should be abandoned. Therefore, to identify the approach a business should take, all projects require a detailed risk assessment that aims to identity, quantity and provide a means to manage risk. This process can be undertaken as a comparison – expressed on a matrix – of two variables per risk. The likelihood is compared against the consequence and assigned a rating with a predetermined level to quantify the level of risk and the predetermined company response (Marcelino-Sadaba, Perez-Ezcurdia, Echeverria Lazcano, & Villanueva, 2014). An example of this displayed in the traditional matrix format can be seen in Figure 1 below:

Figure 1: Risk Analysis Matrix
Source: adapted from Marcelino-Sadaba, Perez-Ezcurdia, Echeverria Lazcano, & Villanueva (2014)

This representation allows for clear and concise quantification of risks, as well as rapid identification of what the company is willing to commit to from an action point of view surrounding this risk in line with business risk appetite.

As discussed by Larson; Et al (2017) and visually represented in figure 3.2 below, which has been adapted to show OTC’s preferred time for risk mitigation within the project timeline. Risk migration and correction have a direct financial correlation to when an event occurs in the timeline of a project. Risks mitigated earlier have a lower overall cost and therefore less budgetary impacts. In the context of OTC as a SME with limited financial capacity, early risk mitigation will ensure not just project viability, but potentially overall business viability.

Figure 2: Risk Project Life Cycle
Text Box: “ * “ Represents  MTC preference for risk mitigation in project timeline
Source: adapted from Invensis Learning Pty Ltd (2018)
Onsite Testing & Calibration adopts a 4-step process in regards to risk analysis and mitigation that follows the overall process outlined by Larson; Et al (2017); as well as the process demanded of the business in line with applicable certifications (International Organisation for Standardization, 2016) where the business:

  1. Assesses and Identifies Risks
  2. Controls the Risks
  3. Assesses the effectiveness of controls
  4. Review and monitor to ensure ongoing control effectiveness and to prevent risk escalation.

Specifically addressing OTC’s PPN expansion project,  Appendix 1: OTC PPN expansion risk and mitigation plan sets out a risk assessment for OTC’s PPN expansion in line with the matrix presented in Figure 3.1, This table also expands on a face value risk analysis as it identifies an initial risk rating, and a risk rating post mitigation strategies which are also outlined in the same table.




4.    Major stakeholders and project roles identified, with initial communication requirements outlined


4.1 Major Stakeholders & Roles

As defined by Larson; et al (2017) stakeholders are individuals or organisations that are involved in the project, or whose influence can impact the success or failure of the project. Their positions, needs, expectations and influence can vary greatly. Which is why stakeholder analysis is an important tool to identify the number, needs and expectations of relevant stakeholders, and how they interact or can impose on the project, allowing their roles and influence on the project to be determined (Larson; Et al; 2017).
Table 3 outlines the various identified stakeholders in OTC’s PPN expansion project, as well as outlining their role(s) within the project. As OTC is a SME, internal stakeholders have multiple roles which as discussed by (Turner, Ledwith, & Kelly (2010) is to be expected as the business size does not permit for specialise project staff to be hired.

Table 3: Stakeholders and their PPN project Roles
Stakeholder
PPN Expansion Project Role
OTC Chief Executive Officer
●        Oversight
●        Strategic steering
●        Provision of finance
●        Final decision maker (if conflict identified)
●        HSEQ duties as required when HSEQ Manager in field training
OTC Chief Operations officer
●        Project Management
●        Equipment ordering (capex)
●        Human Resources duties – appoint new staff
●        Manage and coordinate communication between OTC & PPN
OTC Chief Sales Officer
●        Strategic Planning
●        Marketing
OTC Health, Safety, Environmental & Quality Manager (HSEQ)
●        Guidance and steering of project in line with management system requirements
●        Vehicle Build Assistance (as former technician & qualified mechanical fitter)
●        Ensure HSEQ systems are compliant with PPN requirements
●        Respond to PPN as required for HSEQ issues
●        On-board new staff
●        Train new staff
OTC Field Services Manager
●        Build vehicles
●        Coordinate subcontractors
●        Select candidates
●        On-board new staff
●         Train new staff
OTC Training Manager
●        Ensure training System accurate for specifics of PPN Contract
●        On-board
●        Training new staff
OTC Laboratory Manager
●        Vehicle build manager
●        Subcontractor management
OTC Technicians
●        Vehicle build as required
●        Deliver vehicles to W.A
●        Train new staff
●        Conduct works required by contract
OTC Storeperson
●        Non-capex equipment ordering
●        Coordinate equipment pre installation in new vehicles
OTC Technician Applicants & Candidates
●        Meet requirements of selection process
●        Complete training and carry out contract work
Subcontractors
●        Provision of goods/services as and when required
PPN Contact and Contracts Manager
●        Point of contact between PPN & OTC
●        Communicate OTC requirements to OTC
OTC Schedulers
●        Facilitate labour for in house vehicle construction withing ongoing operational schedule
Equipment Suppliers
●        Supply Goods as and when required/agreed to

Stefan Olander and Anne Landin (2005) discuss a process for stakehoder management that groups stakeholders in line with their level of intrest and power to display their level of influence over a project. This mapping is applicable for OTC in line with who needs to be kept informed and to what extent. This stakeholder mapping can be seen as relavent to some of OTC’s PPN Expansion stakeholders in Figure 3: Stakeholder mapping. Mapping which also speaks towards how and when these stakeholders should be communicated with as discussed further below.

Figure 3: Stakeholder Mapping
Text Box: MTC CEO & COO.Text Box: MTC TechniciansText Box: PPN RepresentativesText Box: MTC Lab ManagerText Box: MTC HSEQ  & Training ManagersText Box: Suppliers & Subcontractors
Source: Adapted from Olander & Landin (2005)

4.2 Initial Communication Requirements

As discussed above and by Larson; Et al (2017) it has been agreed that due to the complex nature of projects, and this OTC PPN expansion project is complex and involves both internal and external stakeholders all around the world; that communication will have the biggest impact on success, and is a potentially the biggest constraint. Therefore, an effective communications plan is vital to the success of the project and will be a key driver in stakeholder management during the project (Turkulainen, Aaltonen, & Lohikoski, 2015).
 Table 4.3 Communications plan outlines OTC Stakeholders and their communication requirements for the duration of the project.
Table 4.3 Communications Plan
Stakeholder
Communication Requirements
OTC Chief Executive Officer
●        Broad
●        Weekly/Milestone based/ As required
OTC Chief Operations officer
●        Detailed – As required
●        As required/ Milestone based
OTC Health, Safety, Environmental & Quality Manager (HSEQ)
●        Keep in the loop – Milestones/As required
●        Broad - generally
●        Specific – as required
OTC Field Services Manager
●         Specific – As required
●        Timeline based
●        As required - inwards and outwards
OTC Training Manager
●        Broad
●        As required – inwards and outwards
OTC Laboratory Manager
●        Detailed – As required
●        Specific – As required
●        Timeline based
●        As required - inwards and outwards
OTC Technicians
●        Broad – As required
OTC Storeperson
●        Specific - As required
OTC Technician Applicants & Candidates
●        Specific - As required
Subcontractors
●        Weekly in lead up to their involvement
●        Daily during their involvement
●        Specific – As required
PPN Contact and Contracts Manager
●        Specific – As required
●        On Completion
OTC Schedulers
●        Specific – As required
Equipment Suppliers
●        Weekly until equipment delivered and OTC take ownership
●        Specific – As required






5.    Quality and accuracy of financial analysis


5.1 Financial Analysis

While this is the biggest expansion project that OTC has undertaken in its history. It is not the first, therefore this project does have somewhat known costings. Previously organic growth has progressively required more mobile laboratories; however, this project’s main driver is the ability of the business to service its contractual obligations. Due to this past knowledge, cost estimations are considered very accurate. In line with discussion by Larson; et al (2017) estimates are critical to determining project viability and cashflow needs without the risk of padded estimates, which is no different to OTC’s PPN expansion. As some of these costs are to be financed this ability to estimate using the apportionment method based on previous phase estimations to gain quick finance when required will give the business the ability to meet the contract commencement date (Larson; Et al, 2017).

The apportinment method is deemed suitable for financial estimates as the expansion is similar to previous expansions, except that it is on a larger scale. The variables to these costings are not from capex comittments, they are from labour and incidental costs during the project phases of building and training. These incidental costs are also able to be estimated using the apportionment method as they have previously formed part of operational expences – I.E a member of the management team flying interstate to deliver internal training program, or posting job advertiesment on Australian job search boards. These costs are known to the business and can therefore still be factored in under the same methods with relativley high levels of accuracy and certainty.
This said, OTC is aware that there is always the potential for budget overruns, this has been concidered as part of OTC’s risk assessment of the project and can be found in Appendix 1: OTC PPN expansion risk and mitigation plan. Contingency funds are available should they be required. Use of any contingency funding for this project will be at the discretion of OTC’s CEO and managed to ideally prevent its use in order to prevent the misuse or misinterpretation as to that contingency funding is for, as discussed by Baccarini, (2005).



6.    List of references


Baccarini, D. (2005). Understanding Project Cost Contingency - A Survey. QUT Research Week 2005. Brisbane: Queensland University of Technology. Available from https://espace.curtin.edu.au/bitstream/handle/20.500.11937/9641/20855_downloaded_stream_311.pdf?sequence=2&isAllowed=y
Flyvbjerg, B., Holm, M., & Buhl, S. (2003). How common and how large are cost overruns in transport infrastructure projects? Transport Reviews, 23(1), 71. Available from https://doi-org.ezproxy.federation.edu.au/10.1080/01441640309904
Hameri, A.-P., & Nihtila, J. (1997). Distributed New Product Development Project Based on Internet and World-Wide Web: A Case Study. Journal of Product Innovation Management, 14(2), 77-87. Available from https://onlinelibrary-wiley-com.ezproxy.federation.edu.au/doi/epdf/10.1111/1540-5885.1420077
International Organisation for Standardization. (2016, Febuary 26). ISO 9001. ISO 9001: 2016 Quality Management Systems Requirements. Sydney, NSW. Retrieved from https://www.saiglobal.com/PDFTemp/osu-2019-12-14/6772597383/9001-2016.pdf
Invensis Learning Pty Ltd. (2018, February 27). What is Project Life Cycle and its Main Characteristics? Availavle from Invensis Learning Pty Ltd: https://www.invensislearning.com/resources/pmp/what-is-project-life-cycle-and-its-main-characteristics
Jaber, H., Marle, F., Vidal, L.-A., & Didiez, L. (2018). Criticality and propagation analysis of impacts between project. Research in Engineering Design, 29(1), 87-106. Available from https://doi-org.ezproxy.federation.edu.au/10.1007/s00163-017-0254-7
Larson, E. W., Honig, B., Gray, C. F., Dantin, U., & Baccarini, D. (2017). Project Management The Managerial Process. Sydney: McGraw-Hill Education.
Marcelino-Sadaba, S., Perez-Ezcurdia, A., Echeverria Lazcano, A., & Villanueva, P. (2014). Project risk management methodology for small firms. International Journal of Project Management, 327-340. Available from https://www-sciencedirect-com.ezproxy.federation.edu.au/science/article/pii/S0263786313000665
Olander, S., & Landin, A. (2005). Evaluation of stakeholder influence in the implementation of construction projects. International Journal of Project Management, 23(4), 321-328. Available from https://www-sciencedirect-com.ezproxy.federation.edu.au/science/article/pii/S0263786305000232
Snyder Stackpole, C. (2010). A user's Manual to the PMBOK Guide. Hoboken, New Jersey : John Wiley & Sons Incorporated. Available from https://ebookcentral-proquest-com.ezproxy.federation.edu.au
Turkulainen, V., Aaltonen, K., & Lohikoski, P. (2015). Managing Project Stakeholder Communication: The Qstock Festival Case. Project Management Journal, 46(6), 74-91. Available from https://journals-sagepub-com.ezproxy.federation.edu.au/doi/pdf/10.1002/pmj.21547
Turner, R., Ledwith, A., & Kelly, J. (2010). Project management in small to medium-sized enterprises: Matching processes to the nature of the firm. International Journal of Project Management, 744-755. Availavle from https://www-sciencedirect-com.ezproxy.federation.edu.au/science/article/pii/S0263786310000943










7.    Appendices



3.      Appendix 1 – OTC PPN expansion risk and mitigation plan

Identified risk during PPN expansion
Pre-mitigation rating
Mitigation Strategy
Post-mitigation Rating
Delays:
●        arrival of vehicles & equipment
●        subcontractors
●        fit out by OTC
Unacceptable
●        Confirm in writing delivery times and subcontractor bookings with suppliers and contractors
●        Schedule time in technicians/managers calendars to complete in house aspects of project
Acceptable

Applicants not meeting required criteria
Unacceptable
●        Seek referrals from current staff members
●        Cold approaches to competitor’s employees
●        Look through previous applicants
●        Approach labour hire and discuss OTC requirements with them
Acceptable
Vehicles arriving late into WA
Strong
●        One additional week built into schedule for vehicles to leave late or encounter delays whilst driving QLD - WA
Acceptable
Candidates not meeting requirements during pre-employment screening
Strong
●        Shortlist and rank perceived suitability, screen top tier and second tier candidates.
●        Interview all potential candidates.
Acceptable
Candidates not meeting requirements post appointment to position
Strong
●        Preference candidates with relevant experience
●        Training, Quality and Field Services Managers to work one on one with each candidate for their training periods
●        Do not inform second tier candidates they have not been selected until training program complete
Acceptable
Budget Overruns
Strong/Unacceptable
●        Secure fixed priced quotes from suppliers
●        Use known providers as there is pricing history and buying power
●        Use historical information when planning incidentals
●        Use Information available publicly as base of pricing
●        Cash at bank available to be used as contingency funding if required
●        CEO to secure line of credit to be drawn on if required
●        CEO to approve all uses of contingency funds
Acceptable